Toronto Integrated Regional Resource Plan posted

August 15, 2019

The Toronto Region Integrated Regional Resource Plan, which considers the potential for long-term electricity demand growth and varying supply conditions between 2019 and 2040, is now online.  

The plan identifies new capacity and reliability system needs and recommends approaches for addressing a number of end-of-life asset replacements and potential longer-term capacity requirements to accommodate growth and city development.

For background about the study scope, and details about Toronto’s power system needs and plan options, download the full report. Visit ieso.ca for more information about the regional planning process.