Status of System Impact Assessment Applications received on or After April 30, 2005

This list contains all transmission, load, generation and ancillary services connection proposals that have submitted an SIA application on or after April 30, 2005 and subsequently executed an SIA agreement. Queuing principles are not applicable to these proposals. Links are provided for SIA reports.

The following are the possible states of the status column:
  • "Complete" indicates that reports are available for viewing.
  • "Active" indicates that work is in progress.
  • "On Hold" indicates that the assessment was placed on hold because the projects has been delayed.
Projects:
Status:

Last Updated: August 24, 2010

CAA ID Proponent Location Project
Type
Proposed
Size
In-service
Date
Current Status of System
Impact Assessment
Report
2004-176 CANADIAN NIAGARA POWER Cornwall, Eastern Ontario Transmission 150 MVAR
N/A
Complete Final Report
Addendum 1
2005-201 CANADIAN HYDRO DEVELOPERS INC Amherst Island New Generation 24 MW
-
Withdrawn  
2005-202 POWERSTREAM INC. 8000 Dufferin St., Vaughan, ON New Supply Point 175 MW
In-Service
Complete Report
2005-204 VISION QUEST WINDELECTRIC Amberley, Bruce County & Ashfield, Huron Ontario New Generation 75 MW
-
Withdrawn  
2005-205 GREEN BREEZE Central Huron Municipality, Huron County New Generation 79.5 MW
Q3-2007
On-Hold  
2005-206 BARRINGTON WIND ENERGY LTD. Concession A, 9 and 10; Huron-Kinloss Township New Generation 18 MW
-
Withdrawn  
2005-207 FIVE NATIONS ENERGY INC Fort Albany TS New Supply Point 20 MVA
Under Construction
Complete Report
2005-208 HYDRO ONE NETWORKS INC. Kenora Interconnection 400 MW
N/A
On-Hold  
2006-209 HYDRO ONE NETWORKS INC. Oshawa Area New Supply Point 250 MVA
Q2-2011
Active Final Draft Report
2006-211 HYDRO ONE NETWORKS INC. King Township or East Gwillimbury New Supply Point 75 MVA
175 MVA
In-Service
Q2-2009
Active Phase I Report
Phase II Final Draft Report
2006-212 HYDRO ONE NETWORKS INC. Build 50/83 MVA, 230-27.6 kV Transformer Station New Supply Point 83 MVA
In-Service
Active Final Draft Report
2006-214 ONTARIO POWER GENERATION INC. Pickering GS New Generation 76 MW
In-Service
Complete Report
2006-215 HYDRO ONE NETWORKS INC. Cambridge Preston TS Transmission 250 MVA
Q4-2007
Active Final Draft Report
2006-216 REGIONAL POWER INC. Town of Mobert New Generation 11.11 MVA
9.44 MVA
-
-
Withdrawn Final Report
Final Report
2006-220 HYDRO ONE NETWORKS INC. Claireville TS Transmission - Q4-2009
Complete Report
2006-221 HYDRO ONE NETWORKS INC. Meadowvale TS/Halton TS Low Voltage Reactive Compensation 21.6 MVAR
32.4 MVAR
Q4-2008
In-Service
Complete Report
2006-223 HYDRO ONE NETWORKS INC. Porcupine TS, Kirkland Lake TS Reactive Compensation - Q4-2010
Active Final Draft Report
Addendum 1
Diagrams
2006-224 HYDRO ONE NETWORKS INC. Milton-Claire 500kV ROW Intersects R21T/R19T Pleas Transmission - In-Service
Complete Final Report
Addendum 1
2006-225 HYDRO ONE NETWORKS INC. Woodstock, Ontario New Supply Point 41 MVA
In-Service
Active Final Draft Report
2006-226 NORTH AMERICAN PALLADIUM Lac Dec Iles Mine (90km north of Thunder Bay) Additional Load 10
Under Construction
Complete Final Report
2006-227 HYDRO ONE NETWORKS INC. Township of Tosoronto-Cnty Road 5 & County Road 15 New Supply Point - In-Service
Active Final Draft Report
2006-228 HYDRO ONE NETWORKS INC. Town of Red Lake Additional Load - In-Service
Complete Final Draft Report
2006-230 HYDRO ONE NETWORKS INC. Vicinity-Winston Churchill Blvd, North-West Miss New Supply Point - Q4-2010
Active Final Draft Report
2006-231 HYDRO ONE NETWORKS INC. North-West Brampton, Ontario New Supply Point - Q2-2008
Active Final Draft Report
2006-233 HYDRO ONE NETWORKS INC. Detweiler TS, Orangeville TS Reactive Compensation 245 MVAR
Under Construction
Active Final Draft Report
2006-236 BROOKFIELD WIND POWER CORPORATION Near the town of Comber, Southwestern Ontario New Generation 150 MW
-
Withdrawn  
2006-237 BROOKFIELD WIND POWER CORPORATION North of SSM, Twnp of Spider, Northern Ontario New Generation 150 MW
-
Withdrawn  
2006-238 HYDRO ONE NETWORKS INC. Mid-town Toronto Transmission - Q2-2012
Complete Final Report
Post-SIA Report
2006-239 ONTARIO POWER GENERATION INC. 70km Northeast of Kapuskasing New Generation 441 MW
Q1-2012
Complete Final Report

2006-240 TORONTO HYDRO ENERGY SERVICES INC. Toronto, Ontario, Canada New Generation 30 MVA
-
Withdrawn  
2006-241 ONTARIO POWER GENERATION INC. Twnp of Gillies Timber Limit, Dist of Temiskaming New Generation 44 MW

Complete Final Report
2006-245 HYDRO OTTAWA LIMITED Cyrville Road Ottawa New Supply Point - Q3-2008
Complete Final Report
2006-246 HYDRO ONE NETWORKS INC. Richview TS Transmission - Q2-2009
Complete
2006-248 HYDRO ONE NETWORKS INC. On the existing R21T/R19T, Plesant tap R-O-W Transmission - In-Service
Complete Final Draft Report
2006-250 HYDRO ONE NETWORKS INC. Southwestern Ontario Transmission - Q4-2011
Active Final Draft Report
Diagrams
2006-251 TORONTO HYDRO-ELECTRIC SYSTEM LIMITED Metro Tor Conv Ctre & John Street Pumping Station New Generation 11 MW
Under Construction
Complete Report
2006-252 ONTARIO POWER GENERATION INC. Beck 1 Generation Station New Generation 68.5 MVA
Under Construction
Complete Final Report
Addendum 1
2006-253 HYDRO ONE NETWORKS INC. Woodstock, Ontario Transmission - Q2-2011
Active Final Draft Report
2007-254 ONTARIO POWER GENERATION INC. Mississauga New Generation 900 MW
Q1-2011
Active  
2007-257 HYDRO ONE NETWORKS INC. St. Catherines Area Transmission - Q4-2009
Active Final Draft Report
2007-258 HYDRO ONE NETWORKS INC. City of St. Catherine Transmission - Q4-2010
Active Final Draft Report
2007-259 LAKESHORE GOLD CORP Timmins (Hwy 101 W & 144) Additional Load - Q3-2007
Complete Report
2007-260 HYDRO ONE NETWORKS INC. Aldborough Twp, County of Chatham-Kent New Supply Point 57 MVA
Q4-2010
Complete Final Draft Report
Addendum 1
2007-262 HYDRO ONE NETWORKS INC. Mississagi Area Special Protection System - Q3-2009
Active  
2007-263 HYDRO ONE NETWORKS INC. Municipality of Windsor and Essex County Transmission 500 MVA
-
Withdrawn Final Draft Report
2007-264 HYDRO ONE NETWORKS INC. 9513 Goreway Dr, Brampton (at existing Goreway TS) New Supply Point 175 MVA
Q2-2010
Active Final Draft Report
2007-265 HYDRO ONE NETWORKS INC. Keith TS Transmission Upgrades 500 MVA
Q1-2010
Complete Final Draft Report
2007-266 ONTARIO POWER GENERATION INC. Geographic Township of Gouin, District of Sudbury New Generation 5.6 MVA
Q4-2010
Complete Final Report
2007-267 DOVER WIND POWER PARTNERSHIP North Kent - Chatham Kent Area New Generation 40 MW
-
Withdrawn  
2007-269 HYDRO ONE NETWORKS INC. Multiple Stations New Generation -
Complete Draft Report
2007-270 WIKWEMIKONG UNCEDED INDIAN RESERVE Wikwemikong, Ontario New Generation 124 MW
-
Withdrawn  
2007-272 CPV CANADA DEVELOPMENTS INC. 2384 Dundas Road South, Cambridge, Ontario New Generation 500 MVA
Q2-2010
Active  
2007-273 BROOKFIELD WIND POWER CORPORATION Renfrew Area-Vicinity of Mount Chute GS, East ON New Generation 99 MW
N/A
Active  
2007-274 BROOKFIELD WIND POWER CORPORATION Near Madawas-Vicinity of Wallance TS, Eastern ON New Generation 199.5 MW
N/A
Active  
2007-275 FPLE CANADIAN WIND, ULC Huron County, Ontario New Generation 63 MW
-
Withdrawn  
2007-276 FPLE CANADIAN WIND, ULC Lambton County, Ontario New Generation 249 MW
-
Withdrawn  
2007-277 FPLE CANADIAN WIND, ULC Huron County, Ontario New Generation 87 MW
-
Withdrawn  
2007-278 FPLE CANADIAN WIND, ULC Lambton County, Ontario New Generation 84 MW
-
Withdrawn  
2007-279 BROOKFIELD POWER Aguasabon River New Generation 10 MW
-
Withdrawn Final Draft Report
2007-280 FPLE CANADIAN WIND, ULC Lambton and Middlesex Counties, Ontario New Generation 349.5 MW
-
Withdrawn  
2007-281 BUTTCON LTD. Windsor, Ontario New Generation 14 MW

Complete Final Report
2007-282 KABINAKAGAMI POWER LP Kabinakagami River north Hwy 11, south Roger's Rd New Generation 60 MW
-
Withdrawn  
2007-283 CPV CANADA DEVELOPMENTS INC. 768 Haldimand Rd 55, Jarvis,ON, Lot7, Concession 7 New Generation 1758 MVA
Q4-2012
Active  
2007-284 TERRACE BAY PULP INC. Terrace Bay, Ontario New Generation 29.5 MVA
Q2-2008
Complete Final Report
2007-285 4444388 CANADA INC. Beardmore, Ontario New Generation 10 MW
-
Withdrawn Final Report
2007-286 SKYPOWER CORP. Parry Island, Ontario New Generation 150 MW

Part 1 SIA Comp  
2007-287 AIM POWERGEN CORPORATION County of Chatham-Kent north of Chatham New Generation 99 MW
-
Withdrawn  
2007-288 AIM POWERGEN CORPORATION County of Chatham-Kent Near the Town of Blenheim New Generation 99 MW
-
Withdrawn  
2007-289 AIM POWERGEN CORPORATION Essex County Near the Town of Tilbury New Generation 40 MW
-
Withdrawn  
2007-290 AIRTRICITY CANADA LTD. Chatham-Kent, Municipality New Generation 100 MW
-
Withdrawn  
2007-292 SKYPOWER CORP. Near Foymount, South of Lake Clear New Generation 49.5 MW

Part 1 SIA Comp  
2007-293 AIR ENERGY TCI INC. (TCI RENEWABLES) Vicinity of Adelaide, Adelaide-Metcalfe, Ontario New Generation 74 MW
-
Withdrawn  
2007-294 ONTARIO POWER GENERATION INC. Township of Pinard, District of Cochrane New Generation 28 MVA
Q4-2012
Active  
2007-295 HYDRO ONE NETWORKS INC. Buchanan TS, Middleport TS, Nanticoke TS Reactive Compensation 1700 MVAR
Q2-2009
Active Final Draft Report
2008-296 HORIZON HYDRO INC. Township of Gery, On, Canada New Generation 5 MW
-
Withdrawn  
2008-297 ACCIONA WIND ENERGY CANADA INC. Chatham-Kent Area, South-Western Ontario New Generation 76 MW
-
Withdrawn  
2008-298 HYDRO ONE NETWORKS INC. Vicinity of the Toyota Woodstock Plant New Supply Point & Transmission 117 MVA
Q2-2010
Active Final Draft Report
2008-301 ENBRIDGE INC. Municipality of Kincardine, Ontario New Generation 99 MW
Q4-2011
On-Hold  
2008-302 ENBRIDGE INC. Town of Saugeen Shores, Ontario New Generation 49.5 MW
Q4-2011
On-Hold  
2008-304 WINDSTREAM ELK LAKE INC. Elk Lake, Ontario New Generation 500 MW
-
Withdrawn  
2008-307 WINDSTREAM TEMAGAMI INC. Temagami, Ontario New Generation 100 MW
-
Withdrawn  
2008-309 RICHVIEW RESOURCES INC. Pickle Lake, Ontario New Supply Point 9 MW
Q4-2010
Complete Final Report
2008-310 SUN COKE INTERNATIONAL Nanticoke, ON New Generation 154 MVA
Q1-2011
Part 1 SIA Comp  
2008-312 NORTHGATE MINERALS CORPORATION Matachewan, Ontario New Supply Point - Q4-2010
Complete Final Report
Appendix 1
2008-314 GENGROUTH MERLIN LP. Chatham-Kent, Near Town of Merlin New Generation 99 MW
Q1-2010
Part 1 SIA Comp  
2008-315 BROOKFIELD RENEWABLE POWER INC. Algoma x Mississagi Area New Generation 10 MW
-
Withdrawn  
2008-316 INDEX ENERGY Corporation Whitby TS #1 New Generation 18.75 MVA
Q4-2099
Part 1 SIA Comp  
2008-318 HYDRO ONE NETWORKS INC. Municipality of Windsor and Essex County Transmission 166.6 MVA
Q4-2012
Complete Final Draft Report
2008-319 CANADIAN SHIELD WIND POWER-DIV OF PTERAGEN CANADA Comm. of Garson-Municipality of Greater Sudbury New Generation 100 MW
Q3-2012
Part 1 SIA Comp  
2008-320 POWERSTREAM INC. NW corner of Rodick Rd & Hwy 407, Markham, ON New Supply Point - Q2-2010
Complete Final Report
2008-321 TRANSCANADA CORPORATION Chatham & Kent (S of Tilbury) New Generation 172.5 MW
-
Withdrawn  
2008-322 TRANSCANADA CORPORATION Orangeville New Generation 48 MW
-
Withdrawn  
2008-323 TORONTO HYDRO ENERGY SERVICES INC. 1 Carlingview Dr., Toronto, ON New Generation 56.3 MVA
14.85 MVA
Q4-2012
Q4-2012
Part 1 SIA Comp  
2008-324 ST. MARYS RENEWABLE ENERGY CORP. Sault Ste. Marie, ON, P6A 5P4 New Generation 35.3 MVA
Q3-2011
Part 1 SIA Comp  
2008-325 BOWARK ENERGY LTD. Chatham-Kent; Harwich; Howard & Raleigh townships New Generation 150 MW
-
Withdrawn  
2008-326 AIR ENERGY TCI INC. (TCI RENEWABLES) East of Nanticoke, Ontario New Generation 80 MW
-
Withdrawn  
2008-329 BRAMPTON COGENERATION INC 7656 Bramelea Road New Generation 24.325 MVA
Q3-2010
Part 1 SIA Comp  
2008-331 TWENTY TWO DEGREE ENERGY CORPORATION Holmesville, Central Huron, County of Huron New Generation 200 MW

Part 1 SIA Comp  
2008-332 HYDRO ONE NETWORKS INC. Township of Tilbury West, Essex County New Supply Point & Transmission - Q2-2010
Active Final Draft Report
2008-333 NORTHLAND POWER INC. Park Rd. South, Oshawa, ON New Generation 71.176 MVA
71.176 MVA
38.8 MVA
Q2-2013


Part 1 SIA Comp  
2008-334 IPC ENERGY Twshp of Dawn-Euphemia, Lambton Cty Chatham-Kent New Generation 64
-
Withdrawn  
2008-336 RENEWABLE ENERGY SYSTEMS CANADA INC near Madawaska, Ontario New Generation 49 MW
Q3-2010
Part 1 SIA Comp  
2008-338 CANADIAN HYDRO DEVELOPERS INC North Middlesex New Generation 34.5 MW
Q3-2012
Part 1 SIA Comp  
2008-339 JUWI SOLAR INC. Bradford West Gwillimbury Generation - Solar 50 MW
-
Withdrawn  
2008-340 IPC ENERGY Prince Edwards County New Generation 64 MW
Q2-2012
Part 1 SIA Comp  
2008-341 WINDLECTRIC INC. Amherst Island New Generation 200 MW
Q4-2013
Part 1 SIA Comp  
2008-342 KRUGER INC. Town of Marathon New Generation 25.3 MVA
Q4-2010
Part 1 SIA Comp  
2008-344 BOWATER CANADIAN FOREST PRODUCTS INC. Thunder Bay New Generation 62.64 MW

Part 1 SIA Comp  
2008-346 HYDRO ONE NETWORKS INC. Nanticoke GS and Detweiler TS Reactive Compensation 350 MVAR
Q1-2011
Complete Final Report
2008-347 NORTHLAND POWER INC. Manitoulin Island New Generation 85 MW
-
Withdrawn  
2008-349 AIM POWERGEN CORPORATION Tilsonburg New Generation 50 MW
-
Withdrawn  
2008-351 CITY POWER COGEN LP 110 Progress Ave., Scarborough, Ontario New Generation 50 MW

Part 1 SIA Comp  
2008-352 HYDRO ONE NETWORKS INC. Northern Ontario Reactive Compensation -
Complete Final Report
2008-353 WINDSTREAM WOLF ISLAND SHOALS INC. Offshore on Lake Ontario near Wolf Island New Generation 64
-
Withdrawn  
2008-354 WINDSTREAM WOLF ISLAND SHOALS INC. Offshore on Lake Ontario near Wolf Island New Generation 200
-
Withdrawn  
2009-355 GREAT LAKES POWER - TRANSMISSION Sault Ste. Marie Modified Connection - Q3-2010
Complete Final Report
2009-356 ONTARIO POWER GENERATION INC. Sir Adam Beck #1 GS New Generation 61.6 MW
Q4-2010
Complete Final Report
2009-357 HYDRO OTTAWA LIMITED Ellwood MTS New Supply Point & Transmission - Q2-2010
Complete Final Report
2009-359 DETOUR GOLD CORPORATION Northeastern Ontario Small Non-Impactive Load 120 MW
Q4-2011
Active  
2009-362 JUNGBLUNZAUER CANADA INC 1555 Elm St., Port Colborne, Ont Modified Connection -
Active  
2009-364 KITCHENER-WILMOT HYDRO INC. 1805 Wilmot Center Rd., Baden, Twnshp of Wilmot New Supply Point 79.1 MW
Q3-2010
Complete Final Report
2009-367 BECKER GENERATION Haig Township, District of Algoma New Generation 15.63 MW
Q2-2011
Part 1 SIA Comp  
2009-368 HYDRO ONE NETWORKS INC. Nipigon-Pickle lake Transmission -
Active  
2009-372 Barrick Gold Corp - Williams Mine Williams Mine CTS Transmission Upgrades -
Complete Final Report
2009-374 OAKVILLE HYDRO ELECTRICITY DISTRIBUTION INC. Between Palermo TS & Trafalgar TS New Supply Point -
Complete Final Report
2010-376 Guelph Hydro Electric Systems Inc. Guelph New Supply Point -
Active  
2010-378 HYDRO ONE NETWORKS INC. near the town of Chapple New Supply Point & Transmission - Q4-2012
Active  
2010-382 COMBER WIND LIMITED PARTNERSHIP Town of Lakeshore New Generation 82.8 MW
Q3-2011
Active  
2010-383 INTERNATIONAL POWER CANADA, INC. City of Lakeshore New Generation 48.6 MW
Q3-2011
Active  
2010-387 INVENERGY WIND CANADA ULC Mapleton Township, Wellington County New Generation 67.5 MW
Q4-2011
Active  
2010-388 NEXTERA ENERGY Nanticoke New Generation 125 MW
Q4-2011
Active  
2010-398 CAPITAL POWER Nanticoke New Generation -
Active  
2010-416 NOVA CHEMICALS 104430 Mooretown, ON Additional Load -
Active  
 